West Broad Street Streetscape
Project Summary and Scope
Limits:
W. Broad Street from Laurel Street to Hamilton Street.
Scope:
This project provides for the design and construction of streetscape Improvements such as ornamental lights, brick sidewalks, landscaping and other amenities through this corridor. Additonal improvements includes Drainage/Drop Inlet Improvements,
Pavement Marking/Crosswalk, Curb Extension and Street Furnishings.
Part of the Project Written Studies, Reports, Presentation
Project Milestones
- Design Completion: Fall 2020
- Advertisement: Fall 2021
- Construction: Spring 2022
- Construction Completion: Fall 2023
Project Funding
This Project is funded though Federal Smart Scale Grant: $6,020,000
Project Status Updates
construction started on April 25, 2022.
Permit, information is listed below. For details please call the Department of Planning, Development and Review at 804-646-4169.
TBD
Expenses (costs are reported quarterly)
$2,590,996 Total
Project Contact Information, if you have questions about this project please contact this individual.
For information about the details of any project first contact the public information office for the department running the project. For most projects the following people can help:
- Department of Public Works Yongping Wang Yongping.wang@rva.gov; (804) 646-2467
Performance Measures and Benchmarks
This project is on-time and within budget.
Project Overall Status (Active, Pending or Complete)
Active
Ordinance Information
No information listed to date
Contract Information
N/A