RVA.gov usa Google Translate™ para proveer una traducción genérica en el idioma de su preferencia. Esta aplicación no sustituye su derecho de obtener una traducción profesional provista por la Ciudad de Richmond como parte del Plan de Acceso a Lenguaje. Para solicitar una traducción llame al centro de servicio al cliente  de la Ciudad de Richmond al 804-646-7000 o 3-1-1.

To contact City of Richmond Customer Service, please call 804-646-7000 or 3-1-1.

Mayo Bridges Rehabilitation

Project Summary and Scope

Replacement of Mayo Bridges over James River

Project Milestones

Mayo Bridge – From VDOT on June 20, 2023

The current actives are as follows:

  • Architectural and Historical surveys are taking place Summer 2023
  • The procurement of a consultant who will perform a geotechnical/structural study of the existing piers is finalizing, and expect them to be on site Summer 2023

Next immediate actives are as follows:

  • Procurement of the consultant (same as above) to complete the conceptual concepts/PFI level work including the first public involvement (10% level) anticipated to be Summer 2023
  • Initial public involvement anticipated to be Fall 2023

Future actives (long term, major milestones) are as follows:

  • UDC Conceptual Meeting and finalize project scoping anticipated early 2024
  • Public Hearing anticipated to be mid 2024
  • DB Procurement anticipated to be late 2024
  • Construction Start anticipated to be 2025 for approximately 3 years

Mayo Bridge – From VDOT on August 28, 2023

The current actives are as follows:

  • Architectural and Historical surveys are complete, though follow-up may be necessary once the report is reviewed
  • Geotechnical survey of the bridge sub-structure is underway
  • Sub-structure analysis and validation underway

 Next immediate actives are as follows:

  • HAZMAT survey of the bridge utilities late September
  • Procurement of the consultant (same as sub-structure analysis) to complete the conceptual concepts/PFI level work including the first public involvement (10% level) anticipated to be Fall 2023
  • Initial public involvement anticipated to be late 2023 or early 2024

Future actives (long term, major milestones) are as follows:

  • UDC Conceptual Meeting and finalize project scoping anticipated mid 2024
  • Public Hearing anticipated to be late 2024
  • DB Procurement anticipated to be 2025
  • Construction Start anticipated to be 2026 for approximately 3 years

Project Schedule

Project is VDOT administered

 

Project Funding

Project Estimate - $ 90,000,000

 

VDOT Six Year Improvement Plan

 

Project Status Updates

VDOT project administration agreement executed 2023.01.17

 

VDOT presentation to the City Urban Planning Commission:

UDC Meeting Record

VDOT Mayo Bridge Presentation to UDC 2023.02.09

 

Permits

 

Expenses

City Match to VDOT   $ 103,536.00

 

Project Contact Information, if you have questions about this project please contact this individual.

Project Overall Status (Active, Pending or Complete)

Active

Ordinance Information

Ord 2022-319

Contract Information

N/A