RVA.gov usa Google Translate™ para proveer una traducción genérica en el idioma de su preferencia. Esta aplicación no sustituye su derecho de obtener una traducción profesional provista por la Ciudad de Richmond como parte del Plan de Acceso a Lenguaje. Para solicitar una traducción llame al centro de servicio al cliente  de la Ciudad de Richmond al 804-646-7000 o 3-1-1.

To contact City of Richmond Customer Service, please call 804-646-7000 or 3-1-1.

City News

Press Releases and Announcements

Posted on Mar 28, 2019

Statement from the Joint Construction Team Regarding the Costs of the New Mason Elementary School, Greene Elementary School and the New Middle School on Hull Street to be Named Later

The Facilities Plan adopted by the Richmond City School Board in December of 2017 including the following estimates for new school construction:

    •    George Mason Elementary School:         $25 million
    •    E.S.H. Greene Elementary School:          $35 million
    •    New Middle School on Hull Street:           $50 million

These estimates have been updated now that the procurement process for the design and construction of all three schools has concluded:

    •    George Mason Elementary School:         $36 million
    •    E.S.H. Greene Elementary School:          $42 million
    •    New Middle School on Hull Street:           $62 million

It is now clear the initial estimates, provided in 2017, under-represented the true cost of construction. Both RPS and the city had concerns this might be the case, which is why both entities discussed engaging a third party to evaluate the costs of rebuilding and/or renovating all RPS schools. The RPS administration brought this proposal to the school board on September 4, 2018 (see screen shot below). The cost of such an evaluation was initially estimated at $100,000, to be split evenly between the city and RPS. Upon further investigation, it was found the price would actually be closer to $200,000, or more. Given the higher cost, the school board decided not to proceed.

Proposed Assessment Image

Not only were the initial cost estimates low, they also did not take into account the following:
    •    Construction costs have increased significantly over the past two years.
    •    The size of Greene Elementary School has been expanded from 650 students to 750 students.
    •    Per the policy adopted by the Richmond City Council (Res. 2015-R8-15), all schools must be LEED Silver certified, which adds significant expense.
    •    The current estimates include a 2% contingency, which if not necessary, will go unspent.

Background on the Joint Construction Team

After the passage of the meals tax last year, the City of Richmond and Richmond Public Schools agreed to develop a joint body, the Joint Construction Team (JCT), to manage the process of building new schools. This group includes the CAO, the mayor’s chief of staff, the superintendent, the RPS board chair and other representatives from each agency. The JCT meets weekly for one hour and only proceeds on key decisions when both parties agree. JCT representatives provide monthly updates to the school board and minutes from all JCT meetings are uploaded to RPS “Board Docs.”