Hull Street over Manchester Canal Bridge Replacement
Project Summary and Scope
Replacement of structurally deficient bridge on Hull Street over Manchester Canal
VDOT UPC 113290
Project Milestones
Section 106 Coordination underway
Project plans at 60%
Private Utility (Dominion Energy, Verizon) relocations underway
Project Funding
Project Estimate - $ 10,761,323
City GO Bonds - $ 2,502,000
VDOT Revenue Sharing - $ 2,502,000
State of Good Repair - $ 5,757,323
Total $10,761,323
Project Status Updates
Met with Verizon to discuss relocation of their facilities off of bridge. City to grant Verizon a utility easement.
Section 106 Coordination ongoing.
Section 408 Coordination with Army Corp of Engineers underway.
Documents
Conceptual Plans (dated Jan 2021)
Public Information outreach was held April 7, 2022 to May 12, 2022, comments and responses posted here
Planning Commission conceptual approval here
City to grant Verizon an utility easement on City property O&R
Public Hearing Plans here
Public Hearing presentation boards:
Public Input meeting held August 06, 2025, comments received here
Permits
Expenses
Stage 1 - $189,450.00
Stage 2,3 - $ 204,000.00
Project Contact Information, if you have questions about this project please contact this individual.
- City of Richmond Department of Public Works Thomas Westbrook Thomas.Westbrook@rva.gov
Project Overall Status (Active, Pending or Complete)
Active
Ordinance Information
CAO authorized to execute a standard project agreement
City to grant Verizon an utility easement on City property
Contract Information
N/A