Hull Street over Manchester Canal Bridge Replacement

Project Summary and Scope

Replacement of structurally deficient bridge on Hull Street over Manchester Canal 

VDOT UPC 113290

Project Milestones

Scoping Underway

Project Funding

Project Estimate - $ 6,678,000

City GO Bonds -  $ 2,502,000

VDOT Revenue Sharing - $ 2,502,000

State of Good Repair - $ 1,674,000

 

Project Status Updates

finalizing Stage 1 Bridge report.  Coordinating utility relocations schedule with private utilities.

Public Information outreach was held April 7, 2022 to May 12, 2022   , Comments and responses posted here

 

Documents

Conceptual Plans (dated Jan 2021)

 

Permits

 

Expenses

 

Project Contact Information, if you have questions about this project please contact this individual.

Project Overall Status (Active, Pending or Complete)

Active

Ordinance Information

TBD

Contract Information